* CBRE Safety report
Engage a foundry specialist to undertake a review of the established forge work area to determine the suitability of facilities available for forge activities and develop a SOP for users; Zac discussed with the Safety Officer (Frank), that as this was developed by Alex who is training to be a blacksmith, that should be suficient.
Complete hot works permit prior to usage of the forge and retain records should the SOP require its completion; Dedicated area does not require hot works permit. Not required in the SOP
Mount the fire extinguisher to the wall; - Zac
Provide a first aid kit with burns kit within the forge area; - Zac
Provide a spill kit within the forge area; - Discussed with the Safety Officer (Frank) that this can be a bucket of sand / kitty litter.
Improve management of the electrical cabling at Site; - Improved management around power hammer. Will get completed after they are tagged
Test and tag electrical cables. - Eris to test the electrical cables.
* Vote in a 2IC with the same powers and responsibilities as the team leader who will take over when the team leader is absent. Zac Marcus voted in as 2IC - all for
* Open day in about 12 weeks? What can we make / demo?
ZacF - Flowers
Fraser - throwing spikes / bottle opener
Erir - Knives
Alex - (if available) - hammer on the power hammer
ZacM - bottle opener / leaf
* Fly press - all for
* New gas cage build - all for